Who is responsible for reviewing and finalizing the quarterly schedule in SKED?

Prepare for the Navy 3-M 303 Work Center Supervisor Exam. Utilize flashcards and multiple choice questions, with hints and explanations. Strengthen your readiness!

The responsibility for reviewing and finalizing the quarterly schedule in SKED is correctly assigned to the Department Head. This role typically oversees multiple work centers within a department and ensures that the scheduling aligns with departmental goals and operational needs. The Department Head has the authority to make adjustments based on priorities, resources, and personnel availability, which are integral in crafting an effective schedule.

In this context, the Department Head takes on a leadership role, integrating input from various supervisors and ensuring that the final schedule meets all requirements and compliance standards. This central oversight also helps maintain consistency across different work centers and fosters communication among the various teams involved.

While the Work Center Supervisor is involved in drafting and proposing schedules based on specific operational requirements, the final decision falls under the Department Head's purview. This tiered approach ensures comprehensive oversight and aligns schedules with broader organizational objectives and resources.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy